PROJECT DESCRIPTION:
This phase of the Cerrillos Road project is approximately 1/2 mile long and begins near Cielo Court and ends at Camino Carlos Rey. Improvements will continue those made from Airport Road to Cielo Court which include:
- Storm drain
- New roadway pavement
- Sidewalks
- Bike lanes
- Bus land / right-turn auxiliary lanes
- Median modifications
- Landscaping
- Bus stops
Storm Drain:
- 66” Storm drain will be placed near the center of Cerrillos Road at an approximate depth of 14’.
Curb drop inlet to be constructed in the outside curb line.
Roadway work:
- Curb and gutter
- Sidewalk
- Three driving lanes in each direction
- Left turn lanes at intersections
- Bike lane
- Auxiliary right turn lanes
- Traffic signals
- Street lighting
- Permanent signing and striping
Landscaping of medians and parkways:
- New landscaping in the median and parkways with irrigation
Traffic Controls:
- Minimum of two lanes open in each direction
- Please respect flag personnel and be alert for workers and heavy equipment near traffic lanes.
- Left turns open through median construction marked by orange barrels.
Business and Residential Access in Work Zone:
- Business driveways and side streets open and accessible northbound and southbound
Proposed Design
Plans for Phase IIB have been finalized.
The graphic below illustrates the proposed design for the project.

|
|
|